Mahaveer Sitara
Pushed back 4 years 11 months from Apr 2020
South Bengaluru
Yelachenahalli metro is 1.1 km away, 2 tech parks within 5 km, 139 schools and colleges.
Delivery record
A promoter files a possession date when a project is registered, and files again if it moves. We compare the two for every project here. It is a record of what happened in this area, not a forecast of what will.
4
delivered on the date first filed
3
pushed back at least once
9 months
median slip, among those that slipped
4 years 11 months
the longest slip here
Checked against government records, June 2026
What’s around
Distances are straight lines from the centre of Puttenahalli, not driving routes — so treat them as a guide to what is close, not to how long it takes.
Places and their locations from OpenStreetMap contributors, ODbL.
Homes here
Pushed back 4 years 11 months from Apr 2020
Delivered on the date first promised
Delivered on the date first promised
Delivered on the date first promised
Delivered on the date first promised
Pushed back 8 months from Aug 2021
Pushed back 9 months from Jun 2021
Who builds here
Nearby
What we can’t tell you yet
We publish a price when a builder sends it to us in writing, with the date we received it. We do not publish an average per square foot, because the honest way to work one out is from real transactions and we do not have them yet. Ask us about a specific project and we will ask the builder.