Builder

Chalet Hotels

2 apartments in Bengaluru. 1 still being built. The earliest we hold was registered in 2017.

Their delivery record

All 1 finished Chalet Hotels project we hold was pushed back — by a median of 2 years 11 months.

Every promoter files a possession date when a project is registered, and files again if it moves. We compare the two. It is a record, not a rating — and it is the same arithmetic for every builder on this site.

0

delivered on the date first filed

1

pushed back at least once

2 years 11 months

median slip, among those that slipped

2 years 11 months

the longest slip we hold

The longest is Raheja Vivarea, pushed back 2 years 11 months.

Checked against government records, June 2026

Still being built

1 Chalet Hotels project under construction

Photos on request

We publish builder photos and site visits — never stock images

Chalet Hotels

Raheja Vivarea - Phase 2

Possession: Dec 2026 · date never pushed back

Layouts, size and price on request

View project

Finished

1 Chalet Hotels project already delivered

Photos on request

We publish builder photos and site visits — never stock images

Chalet Hotels

Raheja Vivarea

Possession: Jul 2025 · pushed back 2 years 11 months

Layouts, size and price on request

View project

Prices

We do not publish Chalet Hotels’s prices, because they have not sent them to us.

Layouts, carpet areas and prices come from the builder in writing, and we publish the date we received them. Until then they are on request — we would rather tell you nothing than tell you a number nobody checked. Ask us and we will ask them.

Ask about Chalet Hotels projects →
We hold 2 projects for this builder — fewer than the 3 a builder page needs to say anything the project pages do not, so this page is not listed in search engines.